STC2000C8-8 Linxia Integrated Logistics Park No. 3 plot construction case

  • 2025.02.07

Construction Brief:

The Linxia Integrated Logistics Park project is located in Huangniwan Town, Linxia County, around the Linxia toll station of Kanglin Expressway, and between the east of National Highway 310 and the Oxford River, a tributary of the Daxia River. The total area of the project is 595,009 m2, the total construction area is 363,159.35 m2, the total construction area is 517,502.14 m2, and the total investment is 2.54 billion yuan, of which the construction and security fee is 1,636.05 million yuan. Plot 1 (product display and trading area) has a total construction area of 151,357.45m2, including 13 single-storey steel structure warehousing and distribution trading centers, 4 single-storey steel structure high-standard warehouses, 1 4-storey service center (the basement floor is a fire pool), 1 14-storey comprehensive service building and ancillary buildings: Plot 2 (food processing and R&D area) has a total construction area of 43,132.2m2, including 5 single-storey steel structure warehousing and distribution centers, 1 4-storey office building, 1 fire pool and ancillary buildings: Plot 3 The total construction area of the bulk commodity storage area is 168,669.7m2, including 4 single-storey steel structure warehouses, 4 2-story sorting and processing centers, 1 4-story comprehensive building and ancillary buildings.

Construction difficulties:

The span is relatively large, there is almost no line of sight, and it needs to work closely with the command staff


Construction process:

Linxia Integrated Logistics Park No. 3 plot Shandong Yantai Haishan tower crane demolition work


Testimonials:

The control is more sensitive, all kinds of actions are on call, the speed of each action can be adjusted to be humanized, and the pedal of the electric telescopic on the machine is very well improved. Out of the car, a counterweight truck driver, a crane two people are enough, the machine this car is more mobile, some work does not need a counterweight car, you can come out to work with the counterweight and foot plate on your back, and the operating cost is relatively low.


Lifting parameters:

The span is 47 meters, the main boom is 79 meters, the counterweight is 61 tons, the heaviest lifting weight is 5 tons, the sleeve is 3.8 tons, the rotation is 3.7 tons, and the maximum lifting capacity under the current working conditions is 6 tons

craneConstruction case