Live vlog: We witnessed the 8 days of "electricity coming from the sea......

  • 2021.12.27

Located in Jiangsu, on the coast of the Yellow Sea, the average annual wind speed of wind energy can reach 7.8 meters at a height of 90 meters, which is suitable for large-scale development of offshore wind farms, Jiangsu Yancheng Longyuan Dafeng H4# wind farm is one of them, Sany SCC19000TM undertake important lifting tasks here.

In order to explore the "electricity from the sea" up close, we conducted an 8-day live shooting.


Time: 2021/11/27
Depart from the Xinyang Port Pier and head to the semi-submersible platform of the "Mirage". After 9 hours, carrying more than 30 pounds of equipment, he successfully boarded the offshore platform. At this time, the breath has not yet evened out, and the SCC19000TM is ready to start work.





Time: 2021/11/28
It took 18 hours to complete the lifting of four towers in a row. At three o'clock in the afternoon, he officially went to the cabin, and two hours later, the ballast was smooth. But the wind started to pick up here, and the construction had to be halted temporarily.





Time: 2021/11/29
The four-day cold wave hit, with a gale of level 8 and a wind speed of 18m/s, and all work at sea was stopped SCC19000TM.



Time: 2021/11/30
The sea was turbulent and the wind was howling, and all the cargo ships at sea had docked to take shelter, leaving only the rescue ships still fighting the wind and waves.




Time: 2021/12/01
It is still impossible to carry out the operation today, and in order to wait for a suitable window, all personnel are always ready to fight.







Time: 2021/12/02
In the afternoon, when the wind weakened, it was a good time to hoist, and the workers on the deck got busy and began to hoist the generator set. At 5 p.m., the cargo ship headed towards the platform with three blades, but for safety reasons, engineers decided to wait until the wind and waves were clear before hoisting the blades.





Time: 2021/12/03
The assembly of the first blade began at 7 a.m. and took 13 hours to assemble all of them. At 9 o'clock in the evening, the last step of fan installation was ushered in - the overall hoisting of the impeller.



Time: 2021/12/04
There was an exciting "good" from the intercom, and the 6.45WM of this station was successfully installed. I heard that the next cargo ship will be 5 days away.We immediately packed our bags, rode in a cage and left the "mirage".



The sea operation is beautiful, you can see the magnificent scenery, and the sky is full of stars in the most beautiful sunset. Offshore operations are lonely, and the installation of a wind farm often takes 1-2 months, or even longer. For wind power people who struggle at sea, this is a challenge, but also a kind of courage to chase their dreams.