The Singapore government construction hospital project, the construction depth is required to be 8~11 meters, the pile diameter is 1400mm, and the cumulative pile volume is 1200. The ground is hard, and the underground parking lot is built after the SCM drilling rig is used to improve the formation.
Construction Phase:
The first stage: manually drill 0~9 meters into the loose soil, and spray water to soften the formation at the same time.
The second stage: automatic drilling and grouting by 6.4~9 meters, the lowering speed is controlled at 0.33m/min±0.02, and the speed of the power head is 22r/min.
The third stage: 9m~0m automatic lifting and reverse stirring by the power head, and the lifting speed is controlled at 0.7m/min.
The fourth stage: automatic drilling and grouting from 0~2 meters, the lowering speed is controlled at 0.33m/min±0.02, and the speed of the power head is 22r/min.
The fifth stage: 2 m ~ 0 m automatic lifting and reverse stirring of the power head, the lifting speed is controlled at 0.7m/min.
Summary:The construction depth is 9m, the average time is 15 minutes in the loosening stage, the average time is 7 minutes in the grouting stage, and the average time is 3 minutes in the mixing stage, and it takes 25 minutes to complete a pile in total, about 15 piles a day.