2016.07.15
2007-04
Chongqing
highway
Concrete machinery
The Chongqing Geyueshan Tunnel of the Yuhuai Line has a total length of 4,050 meters. The tunnel passes through karst caves and coal seam gas areas, and the geological conditions are complex, requiring all construction equipment in the tunnel to have explosion-proof functions. China Railway 11th Bureau undertook the construction of 1,850 meters of the import section, and the concrete construction was carried out by 2 Sany HBT60C-1413 explosion-proof pumps and 1 HBT60C pump. In the pumping process, Sany Pump works easily and without failure, and the user is very satisfied.