262MW Wind Power Project Announcement! Sany Renewable Energy and other 3 machine manufacturers pre-won the bid

  • 2022.06.27

  • Polaris

Announcement of the winning candidates for the procurement of wind turbines and tower equipment for the Zhegu 50MW wind power project in Zhegu County, Shannan Cuomei County, Tibet

(Tender Reference: T221100110415)

End time of publicity: June 27, 2022

First, the evaluation of bids

Bid section (package) [001] Three Gorges Tibet Shannan Cuomei County Zhegu 50MW wind power project wind turbine and tower equipment procurement (25MW):

1. Basic information of the winning candidate

The first place of the winning candidate: Harbin Electric Wind Energy Co., Ltd., the bid price: 99.824 million yuan, quality: meet the requirements, construction period/delivery time/service period: 000 days;

The second place of the winning candidate: Zhejiang Yunda Wind Power Co., Ltd., the bid price: 96.624 million yuan, quality: meet the requirements, construction period/delivery time/service period: 000 days;

The third place of the winning candidate: Xinjiang Goldwind Science and Technology Co., Ltd., the bid price: 120.15 million yuan, quality: meet the requirements, construction period/delivery time/service period: 000 days.

Bid section (package) [002] Three Gorges Tibet Shannan Cuomei County Zhegu 50MW wind power project wind turbine and tower equipment procurement (25MW):

1. Basic information of the winning candidate

The first place of the winning candidate: Sany Renewable Energy Co., Ltd., bid price: 90.72 million yuan, quality: meet the requirements, construction period/delivery date/service period: 000 days;

Winning candidate No. 2: Harbin Electric Wind Energy Co., Ltd., bid price: 99.824 million yuan, quality: meet the requirements, construction period/delivery time/service period: 000 days;

The third place of the winning candidate: Zhejiang Yunda Wind Power Co., Ltd., the bid price: 96.624 million yuan, quality: meet the requirements, construction period/delivery time/service period: 000 days.

2. Project Overview

The Three Gorges Tibet Shannan Cuomei County Zhegu 50MW wind power project, with an average altitude between 5000~5065m. The planned installed capacity of this phase of the project is about 50MW, and the planned installed single unit capacity is 3. X MW wind turbines.

Huadian Fu New Energy Development Co., Ltd. Heilongjiang Branch related bidding project, Heilongjiang Huadian Harbin Yilan Jiguanshan Phase III 150MW wind power project wind turbine equipment procurement winning candidate publicity

CHDTDZ033/22-ZJ-03

First, the evaluation of bids

1. Basic information of the winning candidates

【Heilongjiang Huadian Harbin Yilan Jiguanshan Phase III 150MW Wind Power Project Wind Turbine】

The first place of the winning candidate: Shanghai Electric Wind Power Group Co., Ltd., the bid price: 239.70 million yuan, quality: to meet the requirements of the bidding documents, construction period / delivery / service period: to meet the requirements of the bidding documents.

The second place of the winning candidate: Xinjiang Goldwind Science and Technology Co., Ltd., the bidding price: 2400000000 yuan, quality: to meet the requirements of the bidding documents, the construction period / delivery time / service period: to meet the requirements of the bidding documents.

Second, the project situation


PowerChina Guizhou Engineering Co., Ltd., Huai'an City, Jiangsu Province, Sanhe Town, Hongze District, 62.0 MW Wind Farm Project EPC General Contracting Project Wind Turbine Procurement Project Bidding/Transaction Publicity