40 cranes row station, this job for you, what do you do?

  • 2023.08.25

  • Sany crane

On the morning of August 3, on Dongsheng Road, Shen County, Liaocheng, Shandong, nearly 40 unitscraneNeatly arranged, in preparation for the pipe pull back project of the low-carbon intelligent heating project in the urban area.



Due to the comprehensive consideration of safety, environmental protection, cost and other factors, the low-carbon intelligent heating project in Shen County urban area adopts the construction technology of drawing pipes through the section of the Tuxiao River.The pipeline crosses from the bottom of the river, the deepest part is 24m away from the riverbed, the length of the straight section at the bottom is 36m, the total length of the pipe is 684m, and the total weight is 460t. The pipe drawing construction pipeline is divided into water supply pipeline and return pipeline, and the two pipelines are spaced at an interval of 5.3m.


Yan Shufeng, the person in charge of Liaocheng Huancheng Hoisting, introduced: "40 cranes were dispatched for this construction, of which Sany's cranes accounted for nearly 8 percent, with 90 tons, 80 tons, 50 tons, and 25 tons. ”



Compared with ordinary pipes, the weight of the insulation pipe is heavier, the technical requirements for crossing the bottom of the river are higher, and the construction is more difficult.Yan Shufeng said: "There is a certain degree of attention to the selection of equipment tonnage and station. Medium-tonnage vehicles are needed at both ends of the pipeline, with a lifting weight of about 25 tons, while in the middle, which is not so laborious, 25-ton equipment is used, and the lifting weight is about 13 tons. ”



The diameter of a single pipe is 1.2m, and it passes down nearly 600m, and the crane needs to move the swing arm while lifting the pipeline. It is not easy to ensure that 40 pieces of equipment complete the action of feeding the tube at the same time, and the rotation amplitude of each equipment cannot be too different.


Yan Shufeng said: "In order to ensure the consistency of the action, the construction party chooses the same brand of equipment as much as possible. Because the stability and micromobility of the Sany crane are very good, it is basically based on Sany, so it is more tacit to cooperate. At the same time, the construction party has also formulated a detailed construction plan, and strictly implemented the equipment location, distance, lifting weight, rotation and other details to ensure the accuracy and safety in the construction process. ”




In the end, it took only 2 days to successfully complete the pipeline backhauling work through the Tuxiao River section.


The low-carbon intelligent heating project in Shenxian urban area is a warm cause related to people's livelihood and benefiting the people. After the completion of the project, it will improve the intelligent management level of urban heating in Shen County as a whole, provide better and more accurate heating services for the masses, and at the same time achieve energy saving, consumption reduction, green and low-carbon, and finally achieve "ecological heating".



craneConstruction caseApplication scenarios