The day before yesterday, Zhejiang Hopson Hoisting purchased the world's first 9-bridge 4,000 tonsAll-terrain cranesSAC40000T The first crane was successfully completed in the 200,000 kW wind power project in Pingchuan, Baiyin, Gansu Province.


The 6.25MW wind turbine installed in the project has a hub center height of 120m, a cabin weight of 150t, and a total lifting weight of 180t including spreaders. In terms of lifting weight alone, it is a bit overkill to use SAC40000T, and it is the reason for choosing itUnrivalled flexibility of the Nine Bridges。
The project is a typical mountain wind power, with many slopes and sharp bends, and the working face site is very limited:The center of the tower is about 40m away from the cliff edge, and the equipment should complete the U-turn and swing horizontal standing position in a very narrow space after entering the field, and the operating radius is about 24m, in the words of the on-site personnel: 1m long is not enough.


Du Weihui, the project leader, said: "Because of site constraints, it is difficult for cars to enter and put in the ten bridges, and only this nine bridges can meet them. ”
In addition to the advantages of size, the assembly and transition efficiency of the SAC40000T also made the construction party full of praise:

With the advantage of 9 bridges, SAC40000T successfully passed many S-bend challenges

SAC40000T with outriggers/one and two arms to drive to the stand

65 minutes to complete the full installation of Chaoqi

The day before the hoisting, receive the baptism and blessing of Ruixue
The first hanging performance of the SAC40000T,Sun Lei, general manager of Zhejiang Hopson Hoisting CompanyThe review says: "This 9-axle belt boom is very flexible in the mountainous transition, and this time the seat is so small, it only took 4 hours for the branch to group the car. Its humanized design is really good, reducing a lot of time, especially the over-up assembly, 2 over-up only took an hour. There is also a slotted design of the pull plate, which can be connected by one person, which greatly saves assembly time, and the other is to synchronize these with a super mast and a healthy one, such a large car, so high efficiency,No.1”。