After more than two years of intense construction, the Wentan Bridge in Yiyuan New District, Ganxian County, Jiangxi Province is about to usher in the main bridge closure. Here, two Sany SFT160C2 (T6518-10) flat-top tower cranes have been standing here for a long time, and the construction time of a single equipment is as long as 1500 hours.

These two SFT160C2 (T6518-10) flat-top tower cranes entered the site in mid-2022, with a tower height of 50 meters, an arm length of 65 meters, a wire rope quadruple rate, and a maximum lifting weight of 10 tons.

The Wentan Bridge is about 1,240 meters long and connects the Yiyuan New District and Yangtang Area in Ganxian County. The construction is located in the middle of the Gongjiang River, the span is extremely large, and the wind is uncertain, and the bridge still needs to be navigated, these factors put forward strict requirements for the stability and safety of the two SFT160C2 (T6518-10) flat-top tower cranes.
Therefore, before the tower, Mr. Xiao, general manager of Ganzhou Jinming Construction Equipment Leasing Co., Ltd., led the team to conduct several surveys on the site to ensure that the equipment could well meet the needs of the project.

Mr. Xiao, general manager of Ganzhou Jinming Construction Equipment Leasing Co., Ltd., introduced: "We chose this tower crane for two reasons, one is that its performance is good, providing 8 different arm length combinations, which have played a stable role in major projects and can flexibly adapt to different construction conditions. ”
"The second is because it's stable. In bridge engineering, stability is crucial because it is directly related to construction safety and engineering quality. This model has a sturdy structural design and advanced stability control system, which can maintain excellent stability in high wind speed and complex construction environment, and can provide a safe and reliable working platform for construction personnel to ensure the smooth progress of the project. ”

Since the start of construction in December 2020, the SFT160C2 (T6518-10) flat-top tower crane has played a stable role, and the project has advanced rapidly, and up to now, 80% of the total project volume has been completed. At the construction site, workers are putting the finishing touches on the main bridge before closing. Strive to close the bridge at the end of August, and the whole line will be completed and opened to traffic in October.

Road and bridge construction is a project to serve the people's livelihood and a basic project to promote the high-quality development of the city. The Wentan Bridge project is not only of great significance to the Yiyuan New Area and Yangtang Area of Ganxian County, but also represents the ambition and technical strength of China's engineering construction. The completion of this bridge will greatly improve the local traffic situation, promote the development of the regional economy, and bring more convenience and a better life to the people.