2023.10.25
October 2023
Nanchong City, Sichuan Province
highway
Piling machinery
Project Location:Nanchong City, Sichuan Province
Device Model:SR435S
Pile diameter:2200mm
Pile Depth:50~55m
Geology:The height of the cap is 10m, the water depth is 12m, and the silt and fine sand are 22m~30m
30m~40m strong weathered argillaceous sandstone
40m~ weathered argillaceous sandstone in the final hole
Construction technology:Long casing mud wall protection construction technology
Construction Efficiency:The upper part adopts Ф2.2m pick sand fishing bucket for one drilling;
30~40m with Ф1.5m→2.2m pick sand bucket graded drilling;
The 40m~final hole adopts Ф1.5m→Ф1.8m→2.2m pick barrel drilling, pick sand bucket with the construction of graded drilling;
The whole hole forming time is 20~22h.