2023.11.24
October 2023
Zhongshan City
Municipal utilities
Piling machinery
Project Location:Zhongshan City, Guangdong Province
Device Model:SR505
Pile diameter:1500mm、2000mm
Pile Depth:50~60m
Geology:0~12m silty clay
12~50m silty clay and sand layer
50-70m strongly weathered and moderately weathered mixed rock, broken rock
Construction technology:12m long casing and mud wall construction
Construction Method:SR505 weighs 175 tons under construction, according to the thick layer of geological exploration silt and poor bearing capacity of the foundation, in order to ensure the safety of construction, the gravel is used to pave thickly, and the front end of the subgrade box tiling is carried by two pieces of I-beam.
The low speed and slow footage of the silt layer prevent suction drilling and protect the hole wall from shrinkage
The crushed rock is constructed by an extended drill bucket to improve the high verticality of the hole, and the multi-floating pressure prevents the drill bucket from misaligning
The construction of large models should focus on the safety of the construction platform, especially the construction status of the water trestle
The whole hole forming time is 18~22h.