2016.07.15
2007-09
Egypt
Housing construction
Piling machinery
From September 2007 to the present, at the PORT SAID construction site in Egypt, MISR RAYMOND FOUNDATIONS has participated in the piling construction of the construction site using a Sany SR220C rotary drilling drill, which has an embedded system based on the core of the working machine controller and the CAN-BUS bus technology of the United States, which is fully responsible for the monitoring of the engine, hydraulic pump, hydraulic control valve and the whole machine. In this construction, Sany's rotary drilling rig overcame the construction difficulties of 60 meters deep pile and thick clay soil, and completed the task on time with extremely high work efficiency, so that customers can personally experience the quality of Sany equipment.