Excavators
Ask for a price Online store
Service Hotline 400-8878-318
Excavators
Ask for a price Online store
Service Hotline 400-8878-318
Sany Heavy Industry Sany Heavy Industry Co., Ltd. (SH:600031)
Trinity International Sany International (HK:00631)
Sany Renewable Energy Sany Renewable Energy (SH:688349)

Sany double wheel milling debuts in the Greater Bay Area! Sassy and heroic, not afraid of hard rock

  • 2022.07.29

Construction time

July 2022

Construction site

Shenzhen

The type of project

Municipal utilities

Device type

Piling machinery

Double-wheel groove milling machine is a hard stratum wall-forming equipment used for construction in the field of underground space, and can also be used for square pile construction. It is mainly used in the construction of diaphragm walls in the construction of rail transit stations, deep foundation pit support of high-rise buildings, water conservancy and hydropower projects, etc.



(Sany SDC120 on site)


【Project Introduction】

Pingshan Station of Dapeng Branch Line of Shenzhen-Huizhou Intercity Railway is a double-island four-line station, with a length of 660 meters, a three-story three-column and four-span structure underground, and a foundation pit depth of about 28.68~30.88m. The total excavation volume of the station is about 900,000 square meters, of which about 400,000 square meters are excavated for stone and 200,000 square meters for concrete. The enclosure structure of the standard section of the station (the width of the station is more than 50m wide) adopts 800mm/1000mm thick underground diaphragm wall. The foundation pit base of the main body of this station is mainly located in the soil-like strongly weathered granite layer, medium weathered granite layer and slightly weathered granite layer.




【Construction Difficulties】

(1) The rock surface at the east end of the station is high, and the guide wall surface is 3.1 meters down into the weathered granite, which is difficult to operate;

(2) The traffic roads in the construction area of the station are complex, and many traffic diversion are required, and the uncertainty factors of the construction period are many and complex, and the construction organization is difficult;

(3) The hardness distribution of rock formation is uneven, and some groove sections have high hardness and solitary stones, and the hardness of rock formation can reach 90~110Mpa.




【Construction Efficiency】

After the equipment enters the site for construction, the milling depth is from 2.53 meters to 2.98 meters at 4:33~5:28AM, and from 2.98 meters to 3.82 meters at 6:49~8:25AM, and the comprehensive construction efficiency can reach 0.5-0.6 meters per hour. Customer feedback that the performance of the equipment exceeded expectations, and was not inferior to the pure imported equipment in the same competition.


Shenzhen Shenglong Construction has three pure imported double-wheel milling, which is the first time they have purchased domestic double-wheel milling. The customer said that he had purchased two Sany SR415 rotary drilling rigs and trusted Sany's quality and reputation very much, so he did not hesitate to choose Sany double wheel milling this time.


【Product Features】