Construction of energy facilities
crane
On November 27, 2009, Sany SCC9000 crawler crane adopted the LJDB working conditions of 60m main boom, 48m jib and 58m operating radius, and completed the hoisting operation of the nuclear island dome of Unit 1 of Fujian Ningde Nuclear Power Plant. This operation is the world's first 8983 times that crawler cranes produced in China have been used to hoist critical components for nuclear power construction. On August 8, 2010, the crawler crane of Sany SCC9000 made two breakthroughs and successfully hoisted the dome of the nuclear island of the nuclear power plant again. In this hoisting, the Sany SCC9000 crawler crane adopts the LJDB working conditions of 60m main boom, 48m jib, 24m overlifting radius and 52m operating radius, and hoists the dome of Unit 2 of Unit 2 weighing 143t, 11m high and 37m in diameter to a height of 52m in place, and placing it on the shell tube of the nuclear island.