Construction of energy facilities
crane
Category: SCC700 Project Name: Steel Mill Blast Furnace Structure Construction Project Time: July 2010 Project Location: Handan, Hebei Construction Introduction: Construction conditions: The site space is narrow, and the swing radius of the crawler crane is required. Main hoisting workpiece: Name: blast furnace structural parts Weight: 26 tons Hoisting working radius: 8 meters Hoisting frequency (optional items): 2 times a day Equipment working conditions: main boom 33 meters, 35 tons of hook
Hoisting scheme: It takes 2-3 hours of welding time after the structural parts are lifted and installed.