2016.07.15
2011-04
Yangjiang, Guangdong
Construction of energy facilities
crane
On April 29, 2011, at Yangjiang Nuclear Power Plant, the Sany SCC9000 crawler crane adopted the LJDB working conditions of 66m main boom, 54m jib and 24m overlifting radius, and hoisted the dome of Unit 2 nuclear island weighing 150t, 11m high and 37m diameter to 66m in place, and placed it on the shell cylinder of the nuclear island. The hoisting lasted 50 minutes.

Next article: (MG500/1180-WD) Jintong coal mine construction case
share