Drilling into the core, it is not a problem - SR165 helps the comprehensive pipe gallery project of Pingdi cable tunnel in Shenzhen, Guangdong

  • 2021.12.28

Construction time

December 28, 2021

Construction site

Shenzhen, Guangdong Province

The type of project

earthwork

Device type

Piling machinery


Project Overview

Project Name: Shenzhen Pingdi Cable Tunnel Comprehensive Pipe Gallery Project

Construction unit: Shenzhen Special Economic Zone Construction and Development Co., Ltd

Construction unit: China 20th Metallurgical Group Co., Ltd

Project address: Fuping Middle Road, Longgang District, Shenzhen, Guangdong Province11number

Field Devices:SR165

Drilling tool configuration: machine lock rod Φ377×4×12; Φ0.8mRock-socketed double-bottom sand bucket,Φ0.8mBarrel drills

Pile Diameter:0.8m

The project was contracted by a loyal customer of Sany, who owned SanySR280SR285SR405Considering that the construction of signal tower piles, railway foundation reinforcement piles, rural self-built houses and other pile foundations along the railway requires frequent transfers, short construction periods, and limited site conditions, the customer finally chose to be light and flexible, and can be transported with polesSR165

The project is designed with a pile diameter0.8m, pile depth14m, the stratum is mainly soil layer and strong ~ medium weathered sandstone layer, using dry hole construction, and the hole formation time of a single pile is about50min。 The customer happily introduced us to this oneSR165The efficiency is not inferior to other equipment in the same site, and the relatively complete short columnar sandstone core has been taken out many times, which has been praised by customers again and again.