Zhangjiakou, Hebei
Construction of energy facilities
crane
Construction difficulties:Zhangjiakou, Hebei Province, the terrain is dangerous, and the altitude is about2000 meters, the temperature at the top of the mountain is below zero, the wind speed of 10°C is more than 12m/s, the lifting height is more than 80 meters, the lifting weight is about 96 tons, and the site is narrow.
Construction process:Lifting with the main boom only,Within 1 hour, the 2.0 MW wind turbine nacelle assembly weighing 96 tons (including spreaders) was steadily lifted to an altitude of more than 80 meters, and the nacelle was successfully installed in place.
Testimonials:SCC8000A crawler crane has high operating efficiency and good hoisting performance, and the successful completion of the installation task of the first 4.0 MW wind turbine of Mingyang Wind Power Group will surely set off a new red wave in the wind power market.