Huai'an, Jiangsu
Construction of energy facilities
crane
Jiangsu Huai'an 44MW wind power project has a single wind turbine capacity of 2.65MW, and a number of wind turbines with a hub height of 133m and an impeller diameter of 141m have been newly built. The construction time of the project is urgent, and the hoisting equipment is required to complete the transfer within one day.
SAC16000S take on heavy responsibilities, adopt 80m+66m super jib wind power working conditions, 22m amplitude lifting weight of 115t, 0-130m lifting time of 20min. The disassembly and assembly will be completed in 8-10h, and the transfer will be completed within 24h. Fast action and high efficiency.